You are here: Home Government Water Resources Commissioner Soil Erosion inspections Final Inspection

Final Inspection

sod.jpgFinal inspections are required for all soil erosion permits.  The following requirements must be met for closure of a soil erosion permit, unless otherwise indicated;

1. All disturbed area are permanently stabilized* in a manner to prevent soil movement or loss from erosive forces such as rain, ice, gravity or wind;

2. Any temporary SESC controls have been removed; and

3. All permanent erosion control measures are in place and maintained and the site has been established per the approved soil erosion and sedimentation control plan.

4. Additionally, commercial permits shall schedule a final site inspection with the SESC Program.  The inspection will consist of a walk through of the site to insure the site has met the permit requirements.

A Certificate of Completion will be issued by the SESC Program when a site is permanently stabilized and all applicable fees have been paid.  Failure to complete final inspection requirements shall lead to further enforcement set forth within Part 91, the Rules and this Ordinance.

 

* Permanent stabilization is the establishment of vegetation or the proper placement, grading, or covering of soil to ensure its resistance to soil erosion, sliding or other earth movement.  See our Methods of Stabilization for further information.

Document Actions