Greenway Update

— filed under:

The EMU portion of the B2B trail (from Hewitt to Cornell) will be closed for reconstruction from the late afternoon of Wednesday, July 9, until the end of July.  The contractor will be placing barriers and tape onsite to prevent entry to the work area.  

WCPARC has made a serious commitment to expand hike and bike trails in Washtenaw County.  Over a 10 year period, which began in 2000, a minimum of $10 million will be dedicated to trails development. 

NEW!!  Border-to-Border Trail Map

Link to Greenways Maps

WCPARC Trails Update    June 2007

1.   Border to Border trail

The Border to Border (B2B) trail is a multiagency, collaborative project to construct a multiuse trail traversing Washtenaw County, from Livingston County to Wayne County, along the Huron River.  When completed, the 35 mile trail will permit non-motorized travel through the linked open spaces encompassing Washtenaw County's most distinctive natural feature - The Huron River Corridor.  The B2B Trail will enhance the livability of the county's main urbanized area where approximately 70% of its residents live in river-linked communities.  In July 2005, the Washtenaw County Parks and Recreation Commission received an Award of Distinction for Innovation in Public Involvement, Long Range Planning, Land Use and Transportation, and Non-Motorized Transportation for the Border to Border Trail, from the Michigan Transportation Planning Association. 

For implementation purposes, the B2B trail is being developed in 13 segments from Segment A in the northwest (Livingston Co. border) to Segment M in the southeast (Wayne Co. border).  Currently, work is in progress on the following trail segments listed in order of initiation.

Segment J - Dixboro Rd. to Hewitt Rd.

Length 2.0 miles
Partners

Community Foundation for Southeastern Michigan 
Michigan Department of Transportation 

Status Completed November 2004

 

 

Segment D -  Village of Dexter to Delhi Metropark

Length 4.0 miles
Funding

To be determined

Status In Review
Construction Pending

 

 

Segment L1 -  Grove Road, North Bay Park to Ypsilanti Twp. bike trail

Length 0.15 miles
Funding

WCPARC

Status Completed May 2005

 

 

The following projects, led by agencies other than WCPARC, have the Commissions support - financial where shown with an asterisk *.

Segment K - City of Ypsilanti Campus Corridor EMU to Hewitt Rd.

Length 2.5 miles
Partner

Michigan Department of Transportation

Status Completed Summer 2005

 

 

Segment C* -  Hudson Mills Metropark Phase 1, south from North Territorial Road

Length 1.8 miles
Partners

HCMA (project lead); WCPARC
Community Foundation for Southeastern Michigan 
Michigan Department of Natural Resources

Status Design drawings complete
Construction Anticipated to Commence Fall 2007

 

 

Segment L* -  City of Ypsilanti River s Edge Park, south from Michigan Avenue

Length 1.0 miles
Partners

Community Foundation for Southeastern Michigan
WCPARC

Status Conceptual drawings complete
Construction Anticipated 2008

 

 

Segment M -  Ypsilanti Township , Hydro Park North/Bridge Road

Length 0.33 miles
Partners

Michigan Department of Natural Resources
BRG Development

Construction Spring 2007

 

 

2. Trails in County Parks added to existing trails since 2002.

Independence Lake      2.0 miles 2002/2003
Rolling Hills Park 2.0 miles 2002/2003
Parker Mill Park  0.15 miles completed - July 2007

     (Geddes Road bridge to Dixboro Road)

3. Shoulder Widening

Since the year 2000, WCPARC has cooperated with the Washtenaw County Road Commission (Overlay Program) to add 3 ft. paved shoulders to existing roads to accommodate accessibility for non-motorized activities.  The additional cost to widen these roads was paid by the Washtenaw County Parks and Recreation Commission.  To date, approximately 20 miles of paved shoulders have been provided on 11 roads through this collaboration of two County agencies


Year 2000 5 roads 8.4 miles
Stofer Road North Territorial to Werkner; Werkner, Island Lake to M-52 3.2 miles
Liberty Road 1/4 west of Wagner to Zeeb 1.6 miles
Dexter-Chelsea Rd. Island Lake to Parker 0.4 miles
Maple Road M-14 to Huron River Drive 0.9 miles
Dixboro Road Pontiac Trail to M-14 2.3 miles

 

 

Year 2001 4 roads 6.45 miles
Dixboro Road M-14 to Church St. 0.75 miles
Scio Church Road Wagner to Zeeb 2.0 miles
Wagner Road South of Liberty to Waters 2.1 miles
Bemis Road Moon to City of Saline 1.6 miles

 

 

       Year 2002                                      None                       

 

Year 2003 1 road 5.0 miles
Whitmore Lake Road City of Ann Arbor, Barton Drive to Six Mile 5.0 miles

 

 

        Years              
2004 - 2006       
                             None                        

 

 

TOTAL 19.8 miles (approx.)

Other supported projects - Ypsilanti Charter Township bike trail, McCartney Road, Tyler to Grove, 1.2 miles, Fall 2004.

Hitchingham Road, Ypsilanti Township, Bemis to Textile Road, 2.0 miles, Fall 2004.

To date WCPARC has spent or allocated approximately $5 million to nearly 40 miles of trails and paved shoulders that have either been built or are in design development.