Mechanical Inspection Information
What inspections are required for my Mechanical
Permit?*
Washtenaw County Building Department enforces the 2000
Michigan Mechanical Code. Inspections include:
Heating
-
Underground, propane gas lines prior to concealing.
-
Rough, all duct work including that under concrete slabs, before
concealing.
-
Pre-Fab Fireplace Rough, before any work is covered. (Provide
Manufacture's Installation book for inspections.)***
-
Rough, before any work is covered.**
-
Pre-Fab Fireplace Final
-
Final
Air Conditioning
-
Rough, needed if concealed.
-
Final, only if not concealed.
Gas Test
*Trade inspections can be done in conjunction with another
inspection on the same permit without an extra fee. For example, more than
one inspection can be performed per trip and the cost will be the same as
one inspection. The fee is charged per trip.
**Most manufactured homes only need final inspections, because
they have been approved at the factory. Exception: Work to the manufactured
unit that has been field installed and will be covered must have a rough
inspection, including field installed gas lines.
***If you have a mechanical fireplace, the insulation in the
chase and its method of attachment must be inspected by the Building
Inspector. Do not cover, even if you have an approval from the Mechanical
Inspector - that approval is only for the mechanical installation!
What are common violations noted in Mechanical Inspections?
-
Clearance on vents and fireplaces.
-
Firestopping.
-
Gas tests to all gas lines including fireplaces failing due to pressure
loss.
-
Venting to manufactures manuals: Hot water heater, furnaces, and prefab
fireplaces.
-
Equipment/manufacturer's installation instructions on job site for
inspections.
-
Combustion air and make up air.
-
Pressure test on radiant floor heat.
-
Bath fans not installed and vented on rough mechanical inspection.
-
Insulation protection shield on exhaust vents.
-
Wood burning prefab fireplace hearth insulation to manufacturer's
specifications with approved safety strips.
For More Information: